Home

Park Hours & Fees

Recreation

HorseThief Facts

Construction Photos

Building a Dam

Trenching

Piping

Discharge

Drainage

Structure

Hazard Class

Reservoir Elevation

Sales Tax

Pawnee Watershed

Contact Us

 

    Oct. 2008 Construction Photos

July 2008  Photos

Aug. 2008  Photos

Aug. 2008  Photos #2

Oct.  2008  Photos

 Dec., 2008  Photos

June, 2009 Photos

Sept., 2009 Final Photos

 

Click on each picture to see a larger view

Horsethief Reservoir now under construction

Construction Firm:  Max Jantz Excavating, Montezuma, KS

Construction Engineering Firm:  URS Corporation, Overland Park & Denver, CO

A milestone was reached when construction began on the principal spillway the last week of August, 2008.

Shale bedrock was excavated until the desired depth was reached.

When the water elevation in the reservoir exceeds normal pool, water flows over the top of the intake tower, and falls more than 40 feet to the bottom, where it flows into a 60 inch diameter pipe that extends through the dam. As water exits the pipe it travels through an exit works before falling into a stilling basin.

Cracks in the bedrock were cleaned before they were filled with grout.

A level concrete “floor” called a mud mat was poured the length of the pipe.

After pouring the mud mat, the foundation of the 14 feet square by 43 feet tall  intake tower was poured.

Reinforcing bars were grouted into the tower foundation to insure stability of the tower, scheduled to be completed by mid-November.

Pipe supports were poured at regular intervals the length of the mud mat.

After the pipe supports had “cured,” the 405 foot long principal spillway pipe was installed, three 45 foot sections per day.

The pipe was initially spot-welded at each joint. Permanent welds each take a day to complete. After welding and pressure-testing is completed, the entire length of pipe will be enclosed in concrete.

As water exits the 60” pipe, its momentum will be slowed as it flows down into the stilling basin, reducing the risk of erosion in the outlet channel.

Excavation of the outlet channel downstream from the stilling basin.

As water flows down the outlet channel, it re-enters Buckner Creek on the downstream side of the dam.

 

©Copyright 2008
HorseThief Reservoir

BJS Web Site Development